Stuttgart 21

Under Construction
Knoten
Cost
11.5 bn EUR
Responsible
DB InfraGO AG
Corridor
Stuttgart–Ulm

Travel Time Impact

Stuttgart HbfUlm Hbf

Before
54 min
After
28 min

Timeline

Apr. 1994
Project StartTarget completion: Dez. 2019
Jan. 2005
PlanfeststellungTarget completion: Dez. 2019
Feb. 2010
Construction StartTarget completion: Dez. 2021
Dez. 2022
Section CompletedNeubaustrecke Wendlingen–UlmTarget completion: Dez. 2026
Dez. 2026 (projected)
CompletedTarget completion: Dez. 2026Postponed until further notice

Sub-Projects

A major restructuring of the Stuttgart railway node, replacing the existing terminus station with an underground through station. The project includes 57 km of new tunnels under the city and surrounding hills, enabling faster north-south and east-west connections. The Neubaustrecke Wendlingen–Ulm (completed 2022) is a sub-project of Stuttgart 21.

Last updated: 2026-04-13